Baldwin Road Project
  • Utility relocation work is currently underway along the project. Beginning Tuesday, July 18, 2017 Dan's Excavating will begin replacing water mains and removing buildings necessary for the widening of the road. There will be limited traffic interruption this year. 
  • The project will take place in two phases. Phase I is scheduled to start in July and be completed in November 2018. It includes the section of Baldwin between Morgan and Gregory, and will include reconstructing the road as a wide-median four-lane boulevard between Morgan and Judah and a five-lane road between judah and Gregory. Roundabouts will be constructed at the Judah and Gregory intersections.
  • Phase II is scheduled to start in late 2018 and be completed in 2019. Phase II will include construction of a narrow-median four-lane boulevard from Gregory to Maybee, a wide-median four-lane boulevard between Maybee and Waldon and the construction of three roundabouts at the intersections of Waldon, Maybee, and the Great Lakes Athletic Club.
  • 2 year project (2017-2018)
  • Widening of Baldwin Road from Morgan to Gregory Road
  • Addition of 5 roundabouts at Gregory, Waldon, Maybee, Judah, and GLAC (Great Lakes Athletic Center)
  • Improved lighting and Americans with Disabilities Act (ADA) compliant crosswalks
  • Stay connected to the latest project updates here:


  • For questions or concerns about this road project, please contact the Road Commission of Oakland County at 248-858-4804 or email them at dcsmail@rcoc.org
Road Updates
  • July 17th - September 5th - Stadium Drive road closure, East of Lapeer Road (M-24) you will see crews out there to remove and replace a section of Stadium Drive.

  • Beginning July 17th construction will start on Brown Road from Baldwin to Joslyn and on Baldwin Road between Brown and Gregory. Two-way traffic will be maintained.

  • July 27th - August 30th you will see concrete slab replacements on Sashabaw Road from Maybee to Waldon